|
The Operations Evaluations Department (OED) of the ADB has
presented a bleak picture of the NDP which is part of the government’s 25-year
drainage investment envisaged in 1993 under the Drainage System Environmental
Assessment for which loans were provided by the ADB and World Bank (WB).
The OED’s project completion report states that the NDP had envisaged 28 outputs
under the institutional reforms and drainage investment components, of which
only three were completed and seven partly completed.
‘The remaining 18 activities were not initiated,states he report.
In NWFP and Sindh, some of the maintenance and rehabilitation works implemented
had not been sustainable- with drains already reverting to their pre-works
conditions by project completion. The reluctance of the project implementing
agencies (IAs) to comply with land acquisition and resettlement framework agreed
to as part of the project designs was one of the reasons.
The report has also termed the ADB’s own performance as ‘unsatisfactory’ besides
observing that the national and provincial governments lacked commitment to the
sector reforms and were unable to deliver on institutional reforms in a timely
manner.
While, criticising the ADB, which has also contributed loans to the project, the
evaluation department of the bank has observed that despite the sending of the
12 special loan administration missions, six loan review missions and a midterm
review mission by the ADB, the implementation of the project ‘failed to
improve’.
In Balochistan, the project’s component included (a) rehabilitation of about 20
km of sub-drains and construction of new on-farm drainage facilities for about
2,000 hectares, (b) modernisation of the management of the Pat Feeder canal
system, and (c) rehabilitation of selected distribution canals (d); and
performance contracts for about 300 km of drains. Pilot initiatives for
decentralisation of system management were also included.
In NWFP, the subcomponent comprised (a) the transfer of about 220 shallow tube
wells (STWs) in fresh ground water areas, rehabilitation of about 300 km of
subdrains, and construction of new on-farm drainage facilities for about 2,500
hectares; (b) modernisation of the management of NWFP’s major canal systems and
rehabilitation of selected distribution canals; and (c) performance contracts
for about 1,700 km of drains and about 60 STWs, as well as pilot initiatives for
decentralization of system management.
In Sindh, the only component involved was rehabilitation and improvement of
about 400 km of sub-drains, transfer of about 1,300 STWs in fresh ground water
areas, replacement of STWs in saline ground water areas, and construction of new
on-farm drainage facilities for about 2,500 hectares.
The work on the project was started in 1998 which remained till the end of 2007.
It was expected to lead to physical improvements in drainage and better drainage
operation and maintenance (O&M), with direct impacts for an improved environment
and increased agricultural production. Increases in farmer incomes were expected
to be up to 30 per cent, depending on local conditions.
The report says that objectives of the project were clear and relevant to the
sector, the project design was, however, overly complex and ambitious. The
provision of adequate drainage was itself a daunting task, without including
institutional reforms that diverted attention from the objective of improving
drainage infrastructure and performance.
In effect, the project design set too many objectives to be achieved in order to
reach its intended goal. The design identified the risk that if institutional
reforms did not proceed as envisaged, progress on infrastructure would be
inhibited and the intended benefits of the project jeopardised.
The report cites the failure to implement key policy reforms and insufficient
commitment from the Water and Power Development Authority (Wapda) and the
provincial irrigation and drainage authorities (PIDAs) to implement
institutional reforms for their own organisations as the reasons behind the
inability of the project to achieve its goals.
The actual project cost was far lower than the appraisal estimate. This was
mainly because the project could not be implemented as envisaged and most of the
planned activities were not undertaken. At appraisal, the project was estimated
at $185 million, funded by a loan of $140 million from ADB, $40 million from the
government (22 per cent of the total), and $5 million from beneficiaries.
The actual project cost was $31.14 million, of which $5.87 million was financed
by the government (19 per cent) and the remainder from the loan by the ADB and
World Bank (WB).
An amount of $92.9 million was reallocated to other projects. In addition, there
was a partial cancellation of surplus funds of $11.3 million in May 2007. |